Building Projects by Phase
3.16.22 BOE Meeting Presentation
PHASE 1
Jr/Sr. HS Auditorium Roof Replacement (estimated at $459,207)
PHASE 1 – Timeline
Define Scope October 2021
Design Phase November – December 2021
SED Submission Complete December 27, 2021
SED Review & Approval (estimated) January 2022 – March 2022
Co-Op Procurement April 2022
Construction June – August 2022
Project Closeout Fall 2022
PHASE 2
Scope to-be-determined with remaining budget, Target areas:
- Softball Field
- Demolition of Existing Bus Garage & Parking Lot Reconfiguration
- Elementary School Band Room
- Mill and Pave Access Road from Jr/Sr. HS to ES
- New Road from Elizabeth Street Extension (@ Zim Smith) to ES Access Road
PHASE 2 – Timeline
Programming and Design Phase April 2022 – November 2022
SED Review & Approval (est.) December – March 2023
Bidding & Contract Award April-May 2023
Construction June 2023 – Fall 2024
Project Closeout December 2024